What is Resource Leveling? A Complete Guide for Construction Project Managers

Jacob Gibbs
By
Jacob Gibbs
Oct 31, 2024
What is Resource Leveling? A Complete Guide for Construction Project Managers

With construction projects becoming more complex, effective resource management is more critical than ever. Without it, projects can end up behind schedule, over budget, and with burned-out teams. This is where resource leveling comes in to help construction project managers take control, prevent over-allocation of resources, and keep quality intact.

In this guide, we’ll break down what resource leveling is, why it’s important, and how to implement the best strategies and tools. By the end, you’ll know how to keep projects moving smoothly, support your team, and achieve a well-balanced project scheduling.

What is Resource Leveling?

Resource leveling is a project scheduling technique used to adjust a project’s schedule and resource allocation so resources are used efficiently and without overloading team members. This approach balances project demands with what’s available, which is especially important in construction, where materials, labor, and equipment are often limited. Understanding what resource leveling is and using it strategically allows construction project managers to keep projects aligned with timelines and budgets, preventing burnout and delays.

The Importance of Resource Leveling in Construction Project Management

Effective resource leveling offers a range of benefits for construction project managers and teams:

  • Optimizing Resources for Efficiency: Resource leveling helps project managers allocate resources in a way that maximizes productivity and minimizes downtime. This keeps projects flowing and helps avoid costly stops and starts.
  • Minimizing Deficits and Bottlenecks: By redistributing resources based on project demands, managers can prevent bottlenecks that could otherwise hold back progress.
  • Maintaining Project Quality and Timeliness: Resource leveling helps projects stay on schedule and within budget, protecting both quality and timeliness, which are key to successful projects.

When to Use Resource Leveling in Construction Projects

Knowing when to use resource leveling can be key to a project’s success:

  • Identifying Over-Allocation of Resources: When resources are stretched thin, leveling helps adjust timelines or redistribute resources more sustainably.
  • Preventing Team Burnout and Task Overloading: Resource leveling reduces workload strain on team members, improving morale and productivity.
  • Responding to Project Delays and Constraints: When delays occur, resource leveling offers ways to realign tasks and make the best use of resources without sacrificing quality.

Key Methods and Techniques of Resource Leveling

Resource leveling involves several tried-and-true methods that provide different ways to tackle resource allocation based on the project’s needs:

  • Critical Path Method (CPM): This technique highlights tasks critical to project completion. Resource leveling within CPM ensures essential tasks have the resources they need to meet the project’s deadline.
  • Critical Chain Project Management: Similar to CPM but with a focus on buffers, this method allows time for unexpected delays, reducing resource strain.
  • Fast-Tracking: Fast-tracking involves running some project tasks in parallel instead of sequentially. While it can speed up the project, it requires careful leveling to avoid stretching resources too thin.
  • Project Crashing: Project crashing involves adding more resources to speed up critical tasks. Though effective, this method can be costly, so it’s best used when the budget allows.

Real-World Strategies for Resource Leveling

In construction, resource leveling often calls for creative and adaptive strategies to handle real-world limitations. Here are four practical scenarios for applying resource leveling based on your project goals, deadlines, and available resources:

Scenario 1: Adding More Resources with an Extended Deadline

Here, project managers have flexibility with the project timeline and can add resources gradually. This approach works well with a budget that doesn’t allow for a big workforce or expensive equipment right away. For example, instead of hiring a full team upfront, managers might bring in smaller teams as the project progresses.

  • Use Case: Picture a high-rise building project that needs to consider seasonal weather. Instead of hiring all resources at once, managers can bring in teams in phases, adding workers as certain parts of the building reach critical stages. This phased approach keeps costs under control and prevents the project from being overstaffed early on.
  • Benefits: Extending the deadline avoids overloading resources, minimizing burnout and managing costs.
  • Challenges: Extended deadlines may mean higher indirect costs, like longer equipment leases or scaffolding use, which managers need to weigh.

Scenario 2: Adding Resources to Meet the Same Deadline

With a non-negotiable deadline, adding resources may be the only way to keep things on schedule. This often means hiring more workers, renting extra equipment, or subcontracting tasks to keep pace. Managers should carefully assess the budget impact and ensure that adding resources will actually speed up progress.

  • Use Case: Consider an office building scheduled to open on a set date. To meet this deadline, the project manager hires additional carpenters and masons and rents an extra crane, so multiple floors of the building can be worked on at once.
  • Benefits: This approach keeps projects on deadline and helps milestones stay on track without cutting quality.
  • Challenges: Adding resources for a tight timeline can significantly increase costs and requires careful coordination to avoid miscommunication or inefficiencies.

Scenario 3: Using the Same Resources with an Extended Deadline

If adding more resources isn’t an option due to budget or availability, extending the timeline might be necessary. This gives the existing team the time to work at a manageable pace, ensuring quality without exhausting resources. While this may delay completion, it helps avoid overworking the team and equipment, which can lead to breakdowns and costly repairs.

  • Use Case: For a bridge construction project with a tight budget, the project manager can’t bring in additional equipment or personnel. Instead, they work with stakeholders to extend the timeline, allowing the current team to complete tasks without overwhelming them.
  • Benefits: Extending the deadline helps prevent team fatigue and maintains a steady workflow, reducing the risk of costly errors.
  • Challenges: Project sponsors may hesitate to approve deadline extensions, and indirect costs like extended insurance or admin costs may increase.

Scenario 4: Using the Same Resources to Meet the Same Deadline

Meeting the original timeline with the same resources can be the most challenging. This situation requires efficiency and prioritization to ensure resources are used to their fullest. Managers may need to adjust task schedules, focus on high-impact items, or find ways to reduce task time.

  • Use Case: Imagine a hospital construction project with no budget for additional resources but a strict deadline. The project manager prioritizes efficiency, implementing just-in-time deliveries to reduce delays and reallocating existing staff to areas where progress is slow.
  • Benefits: Using resources wisely without extra costs keeps the project within budget and on schedule.
  • Challenges: This high-stakes approach needs careful planning because one delay could jeopardize the timeline. It can be stressful for the team, risking burnout if not managed well.

Tools and Resources for Effective Resource Leveling

To implement resource leveling in a construction project, using the right tools can streamline the process and boost accuracy:

  • Gantt Charts: These help visualize the project timeline, identify overlaps, and enable better resource planning.
  • Project Management Software: Software solutions like Mastt’s project management tools automate resource allocation, track progress, and flag issues early.
  • Network Diagrams and Previous Project References: Mapping dependencies and consulting past project data offer insights into likely challenges and realistic timelines.
  • Estimating and Tracking Resource Needs: Regularly monitoring resource use against forecasts ensures leveling efforts are on track.

Resource Leveling vs. Resource Smoothing: Understanding the Difference

Construction managers often encounter both resource leveling and resource smoothing, but the two aren’t the same. While resource leveling adjusts timelines to balance resource demand, resource smoothing keeps the timeline fixed while redistributing resources to avoid peaks. Understanding the difference between resource leveling vs. resource smoothing is important: resource smoothing is useful for non-critical tasks where timelines can’t shift but resource adjustments are possible. Recognizing when to use resource leveling and resource smoothing allows construction managers to adapt to project requirements more precisely.

Advantages and Benefits of Resource Leveling for Project Managers

Resource leveling brings several benefits:

  • Improving Work-Life Balance and Team Morale: Balanced workloads help prevent burnout, keeping team members motivated and committed.
  • Ensuring Quality Control and Project Success: Proper resource leveling supports consistent quality, meeting both client and regulatory standards.

Mastering Resource Leveling for Construction Success

Resource leveling is an invaluable tool for construction project managers aiming to deliver high-quality projects on time and within budget. By understanding what resource leveling is and learning how to use it—whether through deadline extensions, resource increases, or maximizing current resources—you can tackle resource allocation challenges effectively. A balanced approach helps your team work efficiently, avoid burnout, and maintain quality standards, even with demanding project constraints.

To take your resource management to the next level, consider exploring Mastt’s project management platform. Mastt offers real-time insights, streamlined processes, and essential tools that support projects from start to finish. Explore Mastt to see how our software can make resource leveling easier and help you keep your projects on track.

Jacob Gibbs

Written by

Jacob Gibbs

Jacob Gibbs is a Customer Success Manager with 5 years of experience, focusing on making sure customers are happy and supported. In his role as Customer Success Manager at Mastt, Jacob leads the team in rebuilding processes and improving customer satisfaction. Driven by the mission to ensure customer success, Jacob leads with a hands-on approach, always ready to jump in and help wherever needed.