What is a Project Controls Plan? Examples + Best Practices

Arlene Hidalgo
By
Arlene Hidalgo
Apr 8, 2025
What is a Project Controls Plan? Examples + Best Practices

A project controls plan is one of the most critical—but often overlooked—tools in capital project success. It lays out the “how” behind managing scope, cost, schedule, and risk, all in one integrated framework. In this blog, we’ll unpack what a project controls plan is, explore examples, and walk through proven best practices to help you build one for your next project.

Expect to walk away with a clear understanding of how to write a practical project controls plan, how it supports schedule and budget performance, and how to align your plan with governance standards. And if you're just starting with project controls, this post gives you a strong foundation without overwhelming detail.

TL;DR
A project controls plan defines how to manage cost, schedule, scope, and risk to keep capital projects on track. It provides structure, roles, and tools for performance tracking, improves decision-making, and supports timely delivery across the project lifecycle.

What is a Project Controls Plan?

A project controls plan (PCP) details the processes, roles, and tools for managing cost, schedule, risk, and scope. It uses KPIs to measure success against budget and timelines.

Unlike a generic project plan, a PCP gets specific about:

  • What data will be collected
  • How performance will be measured
  • When interventions will occur
  • Who’s accountable for what

If you’re dealing with an integrated project schedule or need to align with an integrated master schedule example, the PCP is where it all comes together.

Project manager using a laptop with digital workflow and dashboard overlays, representing the use of a project controls plan to track tasks and project progress.
A project controls plan defines how cost, schedule, risk & scope are managed and measured to keep the project on track.

Key Components of a Project Controls Plan

Every successful PCP has key ingredients that ensure consistency, clarity, and control. These elements help formalize how your team tracks performance and adapts to changes.

1. Scope, Schedule, and Cost Control Framework

At the heart of any PCP is the triple constraint: scope, schedule, and cost. Your plan should specify:

  • How the scope will be baselined and controlled
  • What scheduling system will be used (e.g., Primavera P6)
  • How cost estimates, budgets, and forecasts will be managed

This is where concepts like the iron triangle and cost risk analysis play a significant role in setting realistic baselines.

If you’ve ever asked “what is an integrated master schedule?”, this is your answer—it’s part of the control structure, ensuring every task aligns with cost and time objectives.

2. Risk and Change Management Protocols

No plan survives first contact with the real world. That’s why risk management controls and change control management are essential. A comprehensive risk management plan is crucial for identifying and mitigating risks early, allowing for better planning and minimizing the impact on project schedules.

Include steps for:

  • Identifying and prioritizing project risks
  • Setting up a change approval process
  • Integrating contingency planning with earned value analysis

Ensure this section clarifies who signs off on changes and what documentation is needed to support them.

3. Data and Project Performance Measurement Methods

Without real-time data, a plan is just a hope on paper. This section should explain:

  • What metrics will be tracked (e.g., CPI, SPI, key performance indicators or KPIs such as costs, timelines, and return on investment, control chart)
  • Which tools will be used (spreadsheets, dashboards, Mastt, etc.)
  • How often will performance reviews happen

Consider including a sample table or chart showing how performance data feeds into executive dashboards or a performance measurement baseline.

Diagram showing key components of a project controls plan, including scope, schedule and cost control, change management protocols, and performance and data tracking.
Key ingredients ensure PCP consistency, clarity, control, and adaptability.

How to Build a Project Controls Plan: 7 Simple Steps

Writing a project controls plan is easy. Follow these practical steps to ensure your plan is actionable, aligned, and practical from the start.

1. Define Project Objectives and Project Scope

Start by aligning the PCP with the overall project goals. Clarify deliverables, critical milestones, and success criteria based on project controls vs project management distinctions. Involve project stakeholders to ensure the project goals align with their expectations and insights.

2. Identify What You Can (and Can’t) Control

Focus your controls on the realistically manageable variables. Spoiler alert: Mother Nature isn’t one of them.

Project controls work within the project management framework to manage project data, costs, and timelines throughout the project life cycle.

3. Gather Baseline Information

Pull together the initial scope baseline, cost estimate, and schedule. If you’re working with an integrated master schedule, this is where it starts to shape up.

Monitoring project progress is crucial for tracking and reporting on the project's status, informing stakeholders, managing costs, and ensuring the project stays on schedule.

4. Document Your Control Strategies

Write clear, concise protocols for cost loaded schedule, risk management, and variance tracking. Include visuals or tables where possible.

Also, incorporate project control processes to manage project budgets and schedules effectively.

5. Define Roles and Responsibilities

Assign ownership to each element of the PCP. Reference team roles from project controls and program controls as part of this definition. A project manager is crucial in overseeing project controls to ensure projects remain within budget and on schedule.

6. Select Tools and Reporting Cadence

Pick systems that support automation and visibility—whether it’s Power BI, Mastt, or an integrated project controls platform. Set a cadence for reporting and review. Consider using construction project management software to facilitate efficient project control and enhance visibility across projects.

7. Review and Refine Often

Treat the plan as a living document. Update it based on lessons learned, changes in scope, or new data trends. You’ll often find value by combining PCPs with forecast project management techniques. By reflecting on previous outcomes, you can apply insights to enhance decision-making and effectiveness in managing future projects.

Infographic showing 7 steps to build a project controls plan, from defining scope to reviewing and refining.
Build an effective project controls plan in 7 clear, practical steps.

A PCP in Action: Real-World Examples

The cases below show how structured PCPs have been applied across different capital projects to reduce risk, maintain control, and improve outcomes. Project performance is crucial in this context, as it involves monitoring and assessing success through KPIs, ensuring accurate data collection and analysis to identify issues and make necessary adjustments.

Example 1: Mid-Scale Rail Infrastructure Upgrade

  • Project Type: Station accessibility upgrades across multiple sites
  • Value: $120M
  • Duration: 3 years
  • Challenge: Scope creep and change requests were causing schedule slippage

PCP Implementation Highlights:

  • Set up a clear project baseline with a 3-tier WBS linked to an integrated project schedule
  • Required change request forms with quantified cost and time impact
  • Weekly variance reports using s-curve analysis and control chart tracking
  • Monthly executive briefings supported by dashboards

Monitoring the project's progress was crucial in tracking and reporting on project status, ensuring any deviations were identified early, and stakeholders remained informed.

Result: Reduced rework, improved forecast accuracy by 20%, and shaved three months off the overall schedule.

Two construction professionals inspect rail tracks with a laptop and clipboard, illustrating on-site execution of a project controls plan in a rail infrastructure project.
A clear PCP with baselines, change controls & variance tracking cut delays, boosts forecast accuracy, and saves time on an upgrade.

Example 2: Government Health Facility Expansion

  • Project Type: Expansion of regional hospital facilities under a federal infrastructure stimulus package
  • Value: $450M
  • Duration: 5 years
  • Challenge: Delays in approvals and rising construction costs due to supply chain volatility

PCP Implementation Highlights:

  • Integrated risk registers and cost forecasts using forecast project management
  • Used resource histogram to align labor availability with construction sequencing
  • Applied change control management to avoid undocumented scope additions
  • Deployed visual dashboards for weekly client updates
  • Emphasized the importance of monitoring and adhering to the project's schedule to ensure successful project delivery

Result: Enabled rapid reallocation of resources during delays and helped keep budget variance under 5%.

Digital rendering of a healthcare facility under construction, illustrating the use of a project controls plan to manage complex building data and workflows.
Project controls plan manages risk, change & resources to keep a health facility expansion on track and within budget.

Example 3: Major Airport Runway Rehabilitation

  • Project Type: Complete rehabilitation of a primary runway at an international airport
  • Value: $300M
  • Duration: 2 years
  • Challenge: Tight shutdown windows, air traffic constraints, and stakeholder pressure

PCP Implementation Highlights:

  • Developed an integrated master schedule linking all subcontractor activities to milestone windows
  • Used cost loaded schedule to manage cash flow tightly across phases
  • Built contingency response plans within the project control system for inclement weather and unplanned shutdown extensions

Ensuring the project's success was crucial in achieving the desired project outcomes and minimizing resource waste.

Result: Delivered the project on time with zero operational overruns during active runway closures.

Construction worker observing an airplane on the tarmac, symbolizing the role of a project controls plan in managing airport runway rehabilitation projects.
Project controls plan ensures on-time airport runway delivery with cost control, scheduling, and contingency planning.

Best Practices for Using a Project Controls Plan

The following best practices will help bring your PCP to life and drive consistent performance across the project lifecycle. Project teams are crucial in defining and adhering to the project scope, ensuring that goals are met while managing the budget and timelines effectively.

Infographic showing 9 key practices for a project controls plan, such as communication, tools, compliance, and team training.
Key methods to keep your project controls plan effective and on track.

1. Get to Know Your Team: Understand their strengths, workflows, and communication styles. A good plan supports—not frustrates—the team. The project team plays a critical role in monitoring project progress and addressing issues as they arise.

2. Keep Communication Front and Center: Stakeholder alignment and visibility depend on clarity, which ties directly to monitoring and controlling in project management methods.

3. Use the Right Tools (Not All the Tools): Don’t over-engineer the process. Choose tools that offer simplicity, integration, and visibility. Leverage tools like resource histogram visualizations or dashboards.

4. Align With Governance and Compliance Standards: Ensure your plan supports regulatory and organizational compliance requirements—especially when partnering with project control services.

5. Build Flexibility Into the Plan: Even the best project control plans should account for change. Set parameters for controlled flexibility—such as thresholds for variance or predefined change control workflows—so your team can adapt without chaos.

6. Integrate Early and Across Disciplines: The sooner the PCP is introduced, the more effective it becomes. Involve scheduling, cost, risk, procurement, and design teams during its development. Early integration helps avoid silos and supports a more robust integrated project controls framework.

7. Revisit and Update the PCP Regularly: Don’t let your PCP collect dust. Review it monthly, align it with updated performance data, and track lessons learned. Combine insights with forecast project management to improve outcomes continuously.

8. Train Your Team on the Plan: Even a perfect plan is useless if no one understands it. Run workshops or quick training sessions to ensure team members know what’s expected of them, what tools they’ll use, and how to report issues early.

9. Use Visual Management Wherever Possible: Dashboards, timelines, charts, and variance graphs make the plan more digestible. Tools like control charts and s-curve analysis help communicate status at a glance and support faster, clearer decision-making.

Why You Shouldn't Start a Project Without a Controls Plan

Too many projects launch without a clear roadmap for how performance will be tracked and decisions will be made. A project controls plan gives teams the guardrails they need to stay aligned from day one.

Here’s the thing: starting a significant project without a control plan is like building a house without a blueprint. You might get something built, but it won’t be on time, on budget, or even close to what was promised.

A well-crafted project controls plan:

  • Aligns your team and stakeholders
  • Reduces surprises and rework
  • Supports smarter, faster decision-making
  • Enhances transparency and accountability

If you're building or refining your PCP and want to explore modern tools that support real-time performance tracking, schedule integration, and governance compliance, Mastt's platform is a good place to start. From earned value tracking to automated dashboards, the right system can make your project controls plan not just useful, but indispensable.

FAQs About Project Controls Plan

While both are critical documents in capital projects, a project control plan focuses explicitly on how cost, schedule, scope, and risk will be monitored and controlled. In contrast, a project management plan is broader and includes elements like communication, quality, procurement, and stakeholder engagement. The project control plan is often a key subset of the overall management plan, providing the tactical framework for project performance.
A project controller is responsible for implementing and maintaining the project control plan. They track budgets, analyze schedule performance, manage risks, and report variances to project stakeholders. Their role is to ensure that actual performance aligns with the control plan's baselines, and they often recommend corrective actions when issues arise.
The project control plan supports project objectives by establishing a structured approach to measuring success. By defining key performance indicators, baselines, and control mechanisms, the plan helps ensure that milestones are met, budgets are respected, and risks are addressed proactively, ultimately increasing the likelihood of achieving the project's intended outcomes.
Project control specialists bring expertise in cost estimating, scheduling, risk analysis, and earned value management. On large infrastructure projects, they often work alongside project managers and engineers to design and execute the project control plan, ensuring each component such as cost control or schedule monitoring is technically sound, data-driven, and aligned with governance requirements.
Project controlling is vital throughout the entire project life cycle, not just during execution. It begins during planning with the development of the project control plan and continues through design, procurement, construction, and closeout. Continuous project controlling enables proactive risk management, real-time reporting, and informed decision-making at every stage.
Arlene Hidalgo

Written by

Arlene Hidalgo

Arlene is a content marketing expert with over a decade of experience helping construction project management professionals build authority. She creates impactful content that simplifies complex concepts, engages stakeholders, and highlights industry expertise. Her work ensures your projects, insights, and innovations stand out in the competitive construction landscape.