What is a Fragnet Schedule? A Guide to Managing Project Changes

Kristina Eckert
By
Kristina Eckert
Contributor:
Jul 18, 2025
What is a Fragnet Schedule? A Guide to Managing Project Changes

The term 'fragnet' (fragment + network) means a small, focused portion of a project schedule that isolates specific interconnected activities. When disruptions hit your construction project, a fragnet schedule lets you zoom in on just the affected tasks to analyze impacts without touching your entire timeline.

This targeted approach helps project managers quickly assess delays, resource issues, and change orders. Instead of getting overwhelmed by complex schedules, you focus on what matters most: the disrupted activities and their ripple effects. Let's explore how fragnets can transform your construction project management.

TL;DR
A fragnet (fragment + network) is a small portion of a project schedule that focuses on specific interconnected tasks. It lets project managers zoom in on affected activities to analyze how changes or delays impact them without reworking the entire schedule. Fragnets are especially useful for managing change orders and unexpected disruptions. Think of it as isolating a fragment of your network diagram for detailed analysis.

What is a Fragnet Schedule?

A fragnet schedule refers to a smaller, detailed portion of a larger project timeline that focuses on a specific segment or group of activities within the overall project schedule. This technique allows project managers to zoom in on critical or impacted tasks without having to rework or analyze the entire project schedule. Essentially, a fragnet (a blend of "fragment" and "network") highlights a network of activities that are interconnected and whose outcome significantly impacts the larger project plan.

By focusing on these small but crucial segments, project managers can effectively assess potential delays, risks, or variations in the construction timeline. Fragnet schedules help to isolate the impacted sections and identify the ripple effects these disruptions may have on subsequent tasks and resources.

Importance of a Fragnet Schedule in Construction Project Management

In construction projects, the stakes are high, and the margin for error can be thin. Adopting a fragnet schedule brings a targeted approach to dealing with change and enables more refined analysis and decision-making. Here are some reasons why a fragnet schedule is crucial:

  • Focused Analysis for Critical Changes: Fragnet schedules allow project managers to zoom in on specific portions of the project, focusing on areas most vulnerable to changes. This enables managers to conduct more precise analyses and to design customized mitigation strategies for specific issues.
  • Efficient Change Order Assessment: When change orders or unforeseen disruptions occur, a fragnet helps project managers isolate the affected activities and examine their dependencies. This approach allows them to assess the implications of a change order without overhauling the entire schedule.
  • Enhancing Communication and Stakeholder Clarity: Using a targeted fragnet schedule helps in simplifying complex changes. It offers clear insights to stakeholders without overwhelming them with unnecessary details. This leads to better understanding and more effective communication.
  • Resource Reallocation and Delay Mitigation: By identifying where delays are likely to impact the timeline, a fragnet schedule allows project managers to reassign resources and adapt schedules to minimize negative outcomes. This proactive approach is essential in maintaining project timelines and controlling costs.
  • Preserving the Integrity of the Project Timeline: Through focused analysis, managers can identify the interdependencies in smaller groups of tasks and understand their impact on the larger project timeline. This helps preserve the integrity of the overall project schedule.

How to Create a Fragnet Schedule

Creating a fragnet schedule involves isolating the portion of your project schedule that requires focused analysis. This allows for a precise examination of specific changes or delays. Here’s a step-by-step approach:

  1. Identify the Affected Activities: Begin by identifying the activities in the project schedule that are impacted by a change or delay. These activities will form the core of your fragnet. It’s crucial to accurately identify all tasks that might be affected, even if the impact is indirect.
  2. Establish Dependencies: Within your fragnet, clearly define the dependencies and relationships between tasks. Ensure that you’re capturing all the necessary links between tasks, as missing dependencies can lead to inaccurate analysis.
  3. Set the Timeline: Assign start and finish dates to the isolated tasks in your fragnet. This will allow you to measure how disruptions affect your schedule fragment and, consequently, your overall project schedule. Be realistic with your estimates to ensure the fragnet is a reliable reflection of real-world conditions.
  4. Analyze the Impact: Use project management software to simulate and analyze the impact of your fragnet on the larger project scheduling. The goal is to determine whether the isolated disruption cascades into other tasks and if so, what mitigations can be applied.
  5. Communicate the Findings: Prepare a clear report with visual aids, if necessary, to communicate the findings of your fragnet analysis to stakeholders. Visuals like Gantt charts or network diagrams can significantly improve stakeholder understanding.

Common Scenarios for Using Fragnet Schedules

Fragnet schedules can be applied in various scenarios where focused schedule analysis is required. Here are some typical examples in construction projects:

  • Managing Change Orders: When change orders are approved, a fragnet can isolate and analyze the affected portion of the project timeline to assess potential risks and impacts on the overall schedule.
  • Dealing with Unexpected Delays: When unforeseen delays, such as weather disruptions or supply chain issues, affect a critical portion of the project, a fragnet allows managers to explore the ripple effects of the delay and develop mitigation strategies.
  • Assessing Resource Availability: If specific resource constraints arise, fragnet schedules can help project managers analyze the impact on downstream activities and critical paths.

Fragnet Schedule Best Practices

When using fragnet schedules in your construction projects, it’s essential to keep the following best practices in mind:

  • Keep Fragnets Small and Focused: The purpose of a fragnet is to zoom in on a specific issue. Overloading a fragnet with too many tasks can lead to confusion and defeat its purpose. Aim to focus on small groups of interconnected tasks that are directly impacted by the change or delay.
  • Regularly Update Fragnets: Ensure that the fragnet schedules are regularly updated to reflect the current project status and any new changes. Keeping your fragnet schedule up-to-date ensures that it remains an accurate and reliable planning tool.
  • Use Fragnets for Critical Paths: Whenever possible, focus your fragnets on critical path activities to better understand how changes impact the project’s completion date. This way, you’ll get a more accurate picture of the overall project health and can make better-informed decisions.

Key Considerations When Implementing Fragnets

While implementing a fragnet schedule can be highly effective, project managers should be mindful of the following considerations:

  1. Accuracy of Data: Fragnet schedules are only as good as the data used to create them. Ensure that the information about impacted tasks, dependencies, and timelines is accurate and up-to-date.
  2. Clear Communication: Fragnets are an excellent tool for internal analysis, but they must be translated into clear and digestible information for stakeholders. Use visuals and summaries that convey key insights effectively.
  3. Integrated Software Tools: Utilize reliable project management software that allows for fragnet creation and analysis. Tools like Primavera P6 or Microsoft Project offer advanced features for building and integrating fragnets into your main schedule.

Final Thoughts

A fragnet schedule serves as a valuable tool for construction project managers who aim to maintain control over complex timelines amidst unexpected changes. By isolating small segments of a project and focusing on critical activities, managers can more effectively assess and manage the impact of changes, reallocate resources, and maintain the integrity of the overall schedule. With the right approach and a clear understanding of fragnet schedules, you can proactively mitigate risks and keep your construction projects on track.

FAQs About Fragnet Schedule

To create a fragnet in P6, filter your schedule to show just the activities you need to analyze and their connected tasks. Then use the "Create Fragnet" option in the Tools menu to save this as a separate schedule fragment. Many teams now export their P6 fragnets to modern platforms like Mastt for better visuals and easier stakeholder reporting.
A delay fragnet is basically a mini-schedule that zeros in on tasks affected by a specific delay. It shows where the delay started, which activities got pushed back, and how many days the delay impacts your key milestones. They're especially valuable when you need to document delay claims or explain schedule impacts to clients.
A classic fragnet example is when bad weather delays concrete work. Your fragnet might show five connected activities: the delayed concrete pour, the prep work before it, formwork removal after, curing time, and the next structural work. This focused view helps everyone see how a 2-day rain delay actually creates a 5-day schedule impact when you factor in crew availability and curing requirements.
Kristina Eckert

Written by

Kristina Eckert

Kristina Eckert is a product manager with a passion for building tools that make construction project management simpler and smarter. With experience leading product teams across SaaS platforms, she digs deep into user needs and brings people together to build solutions that actually work.